The following construction projects are anticipated to affect highways in Highland County next week. All outlined work is weather permitting. Projects with active or future traffic impacts are linked to OHGO.com.

ONGOING

S.R. 771 Resurfacing — Work began July 31 for a resurfacing project on S.R. 771 between S.R. 138 and the village of Leesburg. S.R. 771 will be reduced to one lane daily from 7 a.m. to 5 p.m., Monday through Friday, with traffic maintained using flaggers. Estimated completion: Fall 2023.

S.R. 41 Bridge Replacement — Work began July 10 for a bridge replacement on S.R. 41 between Birch Lane and the village of Greenfield. S.R. 41 will be closed for 60 days for this construction. During the closure traffic will be detoured via S.R. 28, S.R. 138 and U.S. Route 35. Estimated completion: Fall 2023.

S.R. 41 Resurfacing — Work began June 20 for a resurfacing project on S.R. 41 between the Adams County line and the Pike County line. S.R. 41 will be reduced to one lane daily from 7 a.m. to 5 p.m., Monday through Friday, for this construction. Traffic will be maintained using flaggers. Estimated completion: Summer 2023.

S.R. 73/Mad River Road Safety Improvements — Work began April 17 for an intersection realignment at the intersection of Mad River Road and S.R. 73. During the closure traffic will be detoured via Mad River Road, Powell Road, and S.R. 73. Estimated completion: Summer 2023.

U.S. 50 and S.R. 73 Resurfacing — Work began April 10 for a resurfacing project on portions of U.S.Route 50 and S.R. 73. Work will occur daily from 7 a.m. to 5 p.m., Monday through Friday. One lane of traffic will be maintained throughout construction using flaggers. Estimated completion: Summer 2023. Work on U.S. 50 is between Spickard Road and Fenner Road. Work on S.R. 73 is between U.S. 50 and the Clinton County line

For more information contact the ODOT District 9 Public Information Office at 740-774-8834.

Submitted by the Ohio Department of Transportation.